  • Purpose of the standard – VDA 6.3 is a process audit standard used in the automotive industry. It evaluates the entire product life cycle through seven process elements, P1 through P7.
  • Key changes introduced in the fourth edition (2023) – Remote and hybrid audits were introduced, requirements for embedded software were integrated, and purchasing-related process elements were added to the product and process development stage.
  • Scoring system – VDA 6.3 uses a point-based scoring system (10, 8, 6, 4, and 0). Suppliers are ultimately classified into three categories: A (quality-capable), B (conditionally quality-capable), and C (not quality-capable).

VDA 6.3 Explained: Why Is This Standard So Important in the Automotive Industry?

VDA 6.3 (Verband der Automobilindustrie) is a process audit standard used in the automotive industry to evaluate manufacturing processes in terms of:

  • Assessing the potential of a new supplier or an innovative process
  • Verifying compliance with stringent requirements
  • Identifying potential risks and weaknesses

The VDA 6.3 standard is primarily required by German automotive OEMs (Original Equipment Manufacturers). Unlike IATF 16949, VDA 6.3 is not intended to certify an organization’s entire quality management system. Instead, it focuses exclusively on specific manufacturing processes. It is used for process audits both within an organization and throughout the entire supply chain.

VDA 6.3 is just one of several audit manuals published by the German Association of the Automotive Industry – VDA QMC. These manuals are divided into subject-specific groups designed for organizations performing different functions within the automotive industry. The entire framework includes:

  • VDA 6.1 – Quality Management System Audit; a traditional standard for automotive parts manufacturers, similar in scope to IATF 16949.
  • VDA 6.2 – Quality Management System Audit for service providers, intended for automotive dealerships, logistics companies, and automotive engineering firms.
  • VDA 6.3 – Process Audit, designed to evaluate the product development and series production phases.
  • VDA 6.4 – Quality Management System Audit for manufacturers of machinery and production equipment used in the automotive industry.
  • VDA 6.5 – Product Audit, which evaluates a finished product from the end customer’s perspective.
  • VDA 6.7 – Process Audit for organizations manufacturing machinery and production equipment.
  • VDA 6.8 – Process Audit for services in the supply chain, introduced as a separate standard following its separation from VDA 6.3, Edition 3 (2016).

The currently applicable audit manual is the fourth edition of VDA 6.3, published in 2023. The standard is based on:

  • 35 questions assigned to process element P1.
  • 59 questions, including questions marked with an asterisk (*), covering process elements P2 through P7.

What Changed in the 2023 Revision of VDA 6.3?

The fourth edition of VDA 6.3, published in January 2023, introduced several changes to the standard.

ChangeEdition 3 (2016)Edition 4 (2023)
Number of pages205104
Number of questions (P1)3635
Number of questions (P2–P7)5859

What Changes Were Introduced to Process Element P1 – Potential Analysis?

The main change to Potential Analysis was a reduction in the number of questions from 36 to 35. This resulted from the complete removal of question P 2.7 from the VDA 6.3 standard.

In addition, three questions were removed from Potential Analysis and three new questions were added.

QuestionStatus
P 5.2Removed
P 5.4Removed
P 6.1.5Added
P 6.6.2Added
P 6.3.3Removed
P 6.6.3Added

What Changes Were Introduced to the Asterisk (*) Questions?

The total number of asterisk (*) questions remains unchanged. However, some adjustments were made.

Asterisk (*) AddedAsterisk (*) Removed
P 2.2P 2.5
P 3.4P 4.8
P 6.1.1P 6.3.1

Introduction of Remote and Hybrid Audits

VDA 6.3 addresses industry needs by allowing audits to be conducted remotely or in a hybrid format. The choice of audit format should take the following factors into account:

  • Product criticality
  • Product quality risks
  • Performance indicators
  • Process maturity (VDA MLA)

Introduction of Purchasing-Related Process Elements in P3 and P4

The process elements covering product and process development planning (P3) and implementation of product and process development (P4) have been expanded to include questions related to the purchasing process.

Importantly, both new questions, P 3.4 and P 4.4, are marked with an asterisk (*).

Process element P5 – Supplier Management – remains unchanged.

Automotive SPICE® and VDA MLA

The P elements are now aligned with the Automotive SPICE® process assessment model for software development, as well as with the requirements for assessing the maturity level of new parts under VDA MLA.

What Was Removed from VDA 6.3:2023?

The following chapters and sections were removed from the VDA 6.3 standard:

  • 4. Process Audit – its content is covered by the related standard, ISO 19011.
  • 8. Service Process Audit – transferred to an entirely new standard, VDA 6.8.
  • 10. Best Practices – completely removed.
  • Glossary – moved to the online VDA QMC Glossary.

In addition, process element P6 no longer includes a reference to the assessment of transportation and parts (EU7).

As a result, the fourth edition of the manual has been significantly streamlined in terms of page count.

What Has Remained Unchanged in the New Edition of VDA 6.3:2023?

The main elements that have remained unchanged in the 2023 edition of VDA 6.3 are:

  • The audit structure is still based on process elements P1–P7.
  • The scoring system continues to use numerical values of 10, 8, 6, 4, and 0 (P2–P7), as well as a three-color rating system (P1).
  • Supplier classification continues to follow the same principles and letter-based grading system: A, B, and C.
  • The rules for downgrading the assessment based on asterisk (*) questions remain unchanged.
  • The process is still described using the Turtle Diagram.

Audit Structure (P1–P7)

The VDA 6.3 standard divides process audits into seven key elements. These cover three main phases of the product life cycle:

  • Qualification phase – P1
  • Development and production preparation phase (Pre-SOP / APQP) – P2–P4
  • Series production and after-sales service phase (SOP / Post-SOP) – P5–P7

P1 – Potential Analysis

Potential Analysis is a separate element of the process audit and is used in three situations:

  • Evaluating a new supplier
  • Transferring production to another location
  • Implementing a new manufacturing technology

Supplier Potential Analysis is based on 35 questions selected from the P2–P7 question catalog and marked with the letter X.

The final result is presented using a three-color traffic light rating system:

  • Green – the supplier meets the requirements.
  • Yellow – the supplier conditionally meets the requirements. Implementing appropriate improvement actions before the project starts is recommended.
  • Red – the supplier does not meet the requirements. Corrective actions must be implemented, followed by a reassessment before cooperation can begin.

Importantly, the 2023 edition slightly relaxed the criteria for assigning the lowest rating (red). In borderline cases, the final decision to issue a red rating is now largely based on an official management decision.

Simply put, P1 tells us whether a supplier is capable of meeting our requirements in the first place and what level of quality we can expect once cooperation begins. In essence, it is an extended risk assessment presented in a slightly different format.

P2 – Project Management

Process element P2 marks the beginning of the actual process audit and consists of seven questions. At this stage, we assess how effectively the organization plans and monitors the implementation of a new product.

The assessment covers critical areas of project management, including:

  • Competence of the project management team
  • Planning and availability of the resources required to complete the project (the budget must cover not only production tooling but also equipment used for software validation)
  • Identification of potential project-related risks (e.g., production bottlenecks and logistics issues)
  • Verification of change management processes and how changes are communicated

P2 is not just about “paperwork.” Above all, it assesses the organization’s level of maturity. The following should raise a red flag:

  • Project risks are not addressed or have been defined too broadly.
  • Team members do not know what they are responsible for.
  • The project schedule is not monitored in any way to track progress or ensure deadlines are met.

In short, P2 is all about schedules, budgets, and the team.

P3 – Product and Production Process Development Planning

Process element P3 primarily focuses on verifying how effectively customer requirements are flowed down throughout the organization. In other words, we check whether the project covers all technical and quality requirements specified in engineering drawings, 3D models, specifications, standards, and other applicable documents.

However, meeting customer requirements is not enough. Internal documentation must also be consistent. Here are some important questions to ask: Do the engineering drawing, PFMEA, and Control Plan all tell the same story? Or are there discrepancies between the specified tolerances? For example, if a dimension is specified with a chrome coating in mind, will the part be machined to a correspondingly smaller size to compensate for the additional coating thickness?

The production process design itself must also be reviewed, particularly the elements included in the process flow diagram (Flowchart). Will the planned process steps ultimately ensure that the product meets all requirements? The same approach must be applied to production and inspection tooling, such as injection molds and gauges.

P4 – Implementation of Product and Production Process Development

P4 is the stage where the plans defined in P3 are put into practice on the production floor to verify whether they actually work. As auditors, we confirm whether the planned production process can deliver the expected results in terms of:

  • Quality
  • Cycle time
  • Scrap rate

The following activities and tools help us assess this:

  • PPAP – Is the documentation complete and has it received unconditional approval?
  • Run@Rate – Can the process produce the required quantity of parts within the specified time frame?
  • Availability of qualified personnel – Have operators, inspectors, and setup technicians received adequate training? Are they aware of the risks identified in the FMEA?
  • MSA – Is the measurement system capable of detecting measurement errors?

So, where do things most often go wrong in P4? In engineering practice, this stage verifies whether mistakes were made during earlier phases. If delays in tooling development were overlooked in P2, and machine capabilities were incorrectly estimated in P3, P4 will likely end with frantic production trials and the customer refusing to authorize the start of series production.

P5 – Supplier Management

Even if you plan your project perfectly in P2 and successfully implement it in P4, the entire system remains vulnerable to disruptions without strict oversight of the supply chain. After all, there is a reason people sometimes say that your product is only as good as the materials and components going into it.

Process element P5 requires Tier 1 suppliers to conduct process audits at their Tier 2 sub-suppliers. Having suppliers is not enough – they must be properly qualified. At this stage, the auditor will check, among other things:

  • Whether the supplier holds an IATF 16949 or ISO 9001 certificate, depending on the applicable requirements.
  • Whether a VDA 6.3 P1 Potential Analysis has been performed.
  • Whether the supplier is capable of meeting quality requirements.
  • Whether the company requires its suppliers to meet the same requirements that its customer imposes on it (PPAP).
  • Whether quality objectives are communicated to suppliers.
  • Whether quality performance indicators (PPM) and on-time delivery (OTD) are continuously monitored.

If a supplier delivers defective products more often than conforming ones, the auditor will review the corrective actions taken (e.g., an 8D Report) and how quickly the supplier responds.

P5 is particularly important when pursuing Lean manufacturing. Just-in-Time cannot function properly without close cooperation with suppliers that also maintain consistently high quality standards.

P6 – Production Process Analysis

Process element P6 is the absolute heart of a VDA 6.3 audit. While the previous stages can still be assessed in a conference room, P6 takes place exclusively on the production floor.

The structure of P6 is based on the Turtle Diagram and divides the production process into six key elements:

6.1 Process Input – What Goes In?

We start by verifying whether the semi-finished products delivered to the workstation meet the specified requirements. Material batch traceability is essential, as are system controls that ensure only the correct components are used.

6.2 Process Sequence – How Is the Work Performed?

Both the technology used and the organization of the workstation are critical. We need to check whether the process follows the established plan or whether certain operations are being skipped. Production stability is another important factor, including process capability indices (Cp, Cpk, Pp, Ppk), as well as the system’s ability to detect non-conforming parts and effectively resolve problems through Jidoka.

6.3 Personnel Resources – Who Performs the Work?

This is about confirming that operators know what they are supposed to do and understand the product’s key quality characteristics. Training records, competency matrices, and employees’ awareness of how to respond when an error occurs are all useful sources of evidence.

6.4 Material Resources – What Is Used to Perform the Work?

The assessment covers all production and inspection equipment, including machines, equipment, tools, gauges, and measuring instruments. In this area, the auditor will review aspects such as TPM, calibration, and the overall technical condition of the equipment.

6.5 Process Effectiveness – How Effectively Does It Perform?

The key is to confirm that the process demonstrates its performance under actual operating conditions. The following indicators may be reviewed:

  • OEE (Overall Equipment Effectiveness)
  • PPM (Parts per Million)
  • CoQ (Cost of Quality)

If an indicator is in the red and no action has been taken, we have a problem.

6.6 Process Output – What Comes Out?

At the end of the process, we also assess the finished product or semi-finished product. Quality inspection is important, but so is protecting the product before shipment. This may involve preservation, the use of corrosion inhibitor bags, or appropriate packaging methods. Whatever measures are used, they must comply with customer requirements.

P7 – Customer Care and Customer Satisfaction

Process element P7 focuses on all activities taking place after the product has been delivered to the customer. The most important aspects for the auditor at this stage include:

  • Response to problems and customer complaints – how quickly actions are initiated and how effective they are in resolving the issues.
  • Customer feedback management – what scores the organization receives on customer supplier portals (Scorecards), how this information is communicated internally, and whether corrective actions are taken.
  • Activities throughout the product life cycle – how product quality is maintained and ensured for the aftermarket.

Scoring Model and Classification System

The VDA 6.3 scoring system is based on a five-point scale: 10, 8, 6, 4, and 0, where 10 represents the highest possible score and 0 the lowest. Scores are assigned to the questions included in process elements P2 through P7.

Importantly, the questions provided in the standard serve only as a basis for conducting the audit. They should not be treated as the exact questions to be asked during an audit.

Once the scores have been assigned, the next step is to perform the classification, which determines the final audit result.

The final classification is based on a percentage calculation and divides suppliers into three categories:

  • A – ≥ 90% – Quality-capable supplier.
  • B – < 90%, but ≥ 80% – Conditionally quality-capable supplier.
  • C – < 80% – Not quality-capable supplier.

Asterisk (*) Questions and Downgrading of the Classification

Some questions in the VDA 6.3 standard are marked with an asterisk (*). These questions are critical to the final classification. In essence, they identify critical aspects of the entire process audit.

Their purpose is to protect automotive manufacturers against failures that could have a significant impact on product safety and functionality. Such issues could otherwise be masked by a high average score achieved on the basis of less critical questions. This is why VDA 6.3 places particular emphasis on them.

How does this work in practice?

Regardless of the overall percentage score, if even one asterisk (*) question receives a score of:

  • 4 – the highest possible classification for the supplier is B.
  • 0 – the highest possible classification is C.

Therefore, achieving a high overall percentage score is not necessarily a reason to celebrate just yet. The audit may still result in a C classification, which in many cases can lead to an immediate suspension of deliveries from that supplier.

Summary

VDA 6.3 is a standard that defines process auditing in the automotive industry. It is based on seven process elements, which divide the product life cycle into three phases:

  • P1 – Qualification of a new supplier or innovative process
  • P2–P4 – Product and process development
  • P5–P7 – Series production and after-sales activities

The currently applicable edition is the fourth edition, published in 2023. It includes 35 questions for process element P1 and 59 questions for process elements P2–P7. Some questions are marked with an asterisk (*) to emphasize their importance in terms of product safety and functionality.

The scoring system for process elements P2–P7 is based on a five-point scale (10, 8, 6, 4, and 0). Potential Analysis (P1) uses a traffic-light rating system. The final classification takes into account both the overall percentage score and the scores assigned to individual asterisk (*) questions.

I hope this article has helped you better understand the scope of VDA 6.3 and the principles of conducting process audits in accordance with its requirements. Feel free to share your thoughts in the comments section below. See you next Monday!

FAQ – Frequently Asked Questions

What exactly is the VDA 6.3 standard?

VDA 6.3 is a standard used in the automotive industry to assess manufacturing processes, identify risks, and verify compliance with requirements. It is primarily intended for German OEMs.

Which edition of the VDA 6.3 standard is currently applicable?

The currently applicable version is the fourth edition of the VDA 6.3 manual, published in January 2023.

What are the main elements of a VDA 6.3 process audit?

The audit is divided into seven process elements: P1 covers Potential Analysis, P2–P4 focus on product and process development, while P5–P7 cover series production and after-sales activities.

How are suppliers scored and classified?

A scoring scale of 10, 8, 6, 4, and 0 is used for questions in P2–P7. Based on the percentage score, suppliers are assigned to one of three quality classifications: A (≥90%), B (80–89%), or C (<80%).

What is the significance of questions marked with an asterisk (*)?

These questions identify aspects that are critical to product safety and functionality. A low score on any such question (4 or 0) limits the supplier’s final classification to a maximum of B or C, respectively.

Marcin Ożóg

About the Author: Marcin Ozog

Marcin is a Quality Engineer and auditor with over a decade of experience, primarily in the aerospace industry. He has successfully implemented quality management systems based on ISO 9001 and AS9100 and prepared special processes for Nadcap accreditation. His hands-on experience has taught him how demanding customer collaboration can be and how to build strong supplier relationships. Rather than focusing on dry theory, he analyzes real-world case studies and shares solutions proven in day-to-day manufacturing operations.


Disclaimer
The information presented on this website reflects the author's personal opinions and should not be attributed to any organization for which he has worked or currently works.

Leave a Reply

Your email address will not be published. Required fields are marked *

scroll to the top of the site